File #: 2025-254    Version: 1 Name:
Type: Resolution Status: New Business
File created: 8/4/2025 In control: Operations and Resources Committee
On agenda: 8/13/2025 Final action:
Title: Proposed Change Order No. 1 Contract No. 2201762/SCN-0000301 PS1 Rack and Grit HVAC Upgrade CIP #211011/ BCE Score: 77.50
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Proposed Change Order No. 1

Contract No. 2201762/SCN-0000301

PS1 Rack and Grit HVAC Upgrade

CIP #211011/ BCE Score: 77.50

 

Body                     

Agenda of:                     August 27, 2025

Item No.:                     2025-254

Amount:                     Original Contract                                                               $5,294,101.00

                                          Proposed Change Order No. 1                                     0.00

                                          Total Contract Amount                                          $5,294,101.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     August 4, 2025

 

RE:                     Contract No.  2201762/SCN-0000301

                     PS1 Rack and Grit HVAC Upgrade

                     Vendor:  Clark Construction Company

                     Status: Amendment/Change Order

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2201762/SCN-0000301, Proposed Change Order No. 1, “PS1 Rack and Grit HVAC Upgrade” with Clark Construction Company, with no increase in cost for a cost not to exceed $5,294,101.00 and an increased duration of 117 days for a total duration of 1,037 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

Clark Construction Company (Clark), was awarded this contract for the replacement of existing roof-mounted air handling units, associated ductwork, natural gas piping, controls, and related appurtenances; removal of existing steam unit heaters and their associated components for Pump Station No. 1 (PS-1). To ensure critical equipment and systems remain operational at the facility, the work was required to be completed in phases. Each phase was required to be substantially complete before work could begin on any subsequent phase.

JUSTIFICATION

Early in the project, Clark was directed by GLWA to dismantle and temporarily pause scaffolding activities for approximately one month during work on Phase 1. This was necessary to allow critical chain replacement based on a failure on Grit Collectors No. 4N and 4S to ensure continuity of operations for the WRRF. The chain replacement work could not be performed with scaffolding erected as it would have blocked necessary access for the work to be completed. This interruption resulted in schedule delays and additional costs associated with the dismantling, re-erection, and extended rental of the scaffolding. Additionally, recent unforeseen changes processed under Construction Change Directive No. 05, including brick repair necessary for the installation of exhaust fan no. 1 and ducting repair, further delayed the project’s progress. Based on GLWA’s review, it is infeasible for the Contractor to meet the original contract milestone dates. Therefore, an extension to the substantial completion date and final completion is requested.

PROJECT MANAGEMENT STATUS

Original Contract Time                                            920 days (03/01/2023 - 09/06/2025)

Proposed Change Order No. 1      117 days (09/06/2025 - 12/31/2025)

New Contract Time                                                    1,037days (03/01/2023 - 12/31/2025)

 

PROJECT ESTIMATE

Original Contract Price                                                                $5,294,101.00

Proposed Change Order No. 1                                                           0.00

New Contract Total                                                                                     $5,294,101.00

 

 

 

FINANCIAL PLAN IMPACT

Funding Source: 5421 - Wastewater Construction Fund

Cost Center: 880000 - Capital Improvement Program

Spend Category: Construction

Project Worktag: PRJ-211011

Estimated Cost by Year and Related Estimating Variance: See table below.

Original Contract Price                                                                                                                               $5,294,101.00

Proposed Change Order No. 1:                                                                                                                       0.00

New Contract Total:                                                                                                                                                   $5,294,101.00

Amended Financial Plan Estimate:                                                             $5,294,101.00 

Estimating Variance:                                                                                                                                                       0.00

 

Capital Improvement Plan: No Impact as no additional cost is required.

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on August 13, 2025.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.